Customer: PETROBRAS / ENGINEERING / IECOMPERJ
Objective: Provision of services referring to the elaboration of the executive project, supply of equipment and materials, civil construction, electromechanical assembly and commissioning (preservation, conditioning, pre-operation, startup and guided operation) of the Firefighting System Unit, for the Rio de Janeiro Petrochemical Complex (COMPERJ).
Duration: 1342 days (concluded in January 2016)
Total Man Hours: 2,690,000
Main quantities:
| Excavation | 72,600 m³ |
| Structural Concrete | 8,100 m³ |
| Metallic Structure | 250,000 Kg |
| Pipeline | 4,457,000 Kg |
| Valves | 2,150 un |
| Tank Ø 53m | 720,000 Kg |
| Electrical Ducts | 3,500 m |
| Power and control cables | 52,300 m |
| Pumps 900m³/h | 5 units |